Jackson Streets

Broadway: Flat Creek to Jackson Street

 

Phase I


  • Flat Creek to MacPhails

  • Work through the 5-way intersection
  • Lights will be shut down
  • NO LEFT TURNS will be allowed inside the project limits
  • There will be alternate closures of Pearl Street and Flat Creek
  • Off the road by June 30, 2013 (contractor offered incentives to be done earlier).

PHASE I COMPLETED

Phase II


  • MacPhails to Elks Club

  • NO LEFT TURNS will be allowed inside the project limits
  • Work to begin on August 21, 2013
  • Contract completion date of Nov. 30, 2013